Prediction and Optimization of Roadheader Performance based on Characteristics and Geo-Mechanical Parameters of Rock (Case Study: TABAS Parvedeh coal mine No. ۱)
سال انتشار: 1404
نوع سند: مقاله ژورنالی
زبان: فارسی
مشاهده: 1
فایل این مقاله در 11 صفحه با فرمت PDF قابل دریافت می باشد
- صدور گواهی نمایه سازی
- من نویسنده این مقاله هستم
استخراج به نرم افزارهای پژوهشی:
شناسه ملی سند علمی:
JR_ANM-15-45_001
تاریخ نمایه سازی: 29 دی 1404
چکیده مقاله:
Roadheader machines have good efficiency and flexibility in mechanized tunneling and underground mining. The application of Roadheaders increases the speed of excavation in the tunnels, which dramatically reduces the time and cost of the project. Considering the importance of this issue, this study aims to predict and optimize the penetration rate and excavation speed of Roadheaders using the particle swarm algorithm in Parvadeh No. ۱ mechanized coal mine. Therefore, in this study, the characteristics of Roadheaders have been investigated in related studies. All of these studies were divided into two parts: field observations and laboratory tests. In this research, tunnel number one is considered as the case study, which is divided into ۳۰ parts/sections, and in each section, rock core/sample preparation, the number of joints along the tunnel, excavation time, and volume of the excavated rock mass under the Roadheader machine operation were measured. In the laboratory studies section, the rock core was analyzed by the uniaxial compression strength (UCS) test, and finally, a database was provided based on the obtained results. In the following, nonlinear and linear regression models were used to select the best model for estimating the instantaneous cutting rate (ICR) of the Roadheader machine, which expresses the advancing rate of excavation. In these models, parameters including rock quality designation (RQD) of rock mass, tensile strength (σt), UCS, rock mass brittleness index (RMBI), pick consumption index (PCI), pick consumption factor (PCf), and specific energy (SE) were selected as input variables, and ICR was selected as the output variable. By comparing the results, the linear regression model had the highest determination coefficient and performance index, and the lowest root mean square error. Therefore, this model was selected as the most suitable model. In order to optimize ICR, the relationship obtained from the linear regression model was implemented in the particle swarm algorithm. The results showed that to obtain the optimal limit of ICR in the considered case study with a UCS of ۱.۶۸ MPa and a RQD of ۳۳.۰۹%, ICR is equal to ۳۳.۱۱ cubic meters per hour.
کلیدواژه ها:
Performance prediction ، Roadheader ، Nonlinear and linear regression ، Coal mine ، Particle Swarm Opimization
نویسندگان
Amin Faramarz
Dept. of Mining Engineering, Zarand Higher Education Complex, Shahid Bahonar University of Kerman, Kerman, Iran
Gholamreaz Saeedi
Dept. of Mining Engineering, Faculty of Engineering and Technology, Shahid Bahonar University of Kerman, Kerman, Iran
Ali Hosseini
Dept. of Mining and Metallurgy Engineering, Yazd University, Yazd, Iran
Sajjad Aghababaei
Dept. of Mining Engineering, Faculty of Engineering and Technology, Shahid Bahonar University of Kerman, Kerman, Iran
مراجع و منابع این مقاله:
لیست زیر مراجع و منابع استفاده شده در این مقاله را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود مقاله لینک شده اند :