Occupational risk assessment at the time of construction of a petrochemical unit by JSA method, case study: Abadan Petrochemical
سال انتشار: 1399
نوع سند: مقاله کنفرانسی
زبان: انگلیسی
مشاهده: 229
- صدور گواهی نمایه سازی
- من نویسنده این مقاله هستم
استخراج به نرم افزارهای پژوهشی:
شناسه ملی سند علمی:
OGPC03_010
تاریخ نمایه سازی: 12 آبان 1400
چکیده مقاله:
This cross-sectional study was conducted to identify potential risks and assess the level of risk of activities using the occupational safety analysis technique in March ۱۹۹۸. The level of risk was obtained according to the two parameters of severity and probability of their risk and finally, according to the risk assessment code and their prioritization, control measures were presented. Occupational accident analysis can be effective in identifying and reducing workplace hazards and creating a safe environment and increasing productivity at work. The aim of this study was to identify the risks and assess their risk using occupational safety analysis technique during the construction of an Abadan petrochemical unit and prioritize control and proposed measures using PHA-PRO software. The statistical population of this case study is the jobs involved in the construction of one of Abadan Petrochemical units by JSA method to identify hazards and to collect the required information from JSA team and checklists and job analysis and by proposing control measures to eliminate or reduce the risk level. Potential hazards were used. Conclusion: Based on the results of the study, it is expected that by providing appropriate work tools and personal protective equipment, as well as by implementing the proposed measures, the level of existing risks can be significantly reduced. Among these, simple and cutting workers have the highest number of high risks. Based on the results of the study, seven scaffolding tasks, welding, cutting, electrical repairs, pump repairs, excavation, pipeline replacement and ۷ jobs and ۳۱ tasks were identified using JSA method, a total of ۱۱۴ hazards were identified and ۱۸۵ control measures were performed. Risks and risk assessment for each job were identified and identified, and construction operations risks were at an unacceptable level of ۲.۵%, ۸۲.۵% of the risks at an acceptable level and ۱۵% of the risks at an acceptable level. have taken. Corrective and preventive suggestions are also made to eliminate or limit these risks. Among these, simple and cutting workers have the highest number of high risks and the lowest number of risks related to excavation workers. According to the calculations performed by JSA method based on the obtained criteria, in the first priority of analysis and control measures to reduce risk related to Simple workers and cutters.
کلیدواژه ها:
hazard identification ، risk assessment ، occupational safety analysis ، control measures and corrective suggestions.
نویسندگان
Masoumeh Jahangiri
Student of HSE Engineering Department, Mehr Arvand Higher Education Institute, Abadan, Iran
Amir Hossein Davami
HSE Engineering Department, Ahvaz Branch, Islamic Azad University, Ahvaz, Iran
Keyvan Sheltouki
HSE Engineering Group, Mehr Arvand Higher Education Institute,Abadan, Iran