Construction of the First Cut-Off Wall by a Low Headroom Cutter inside a Dam Tunnel in China

  • سال انتشار: 1389
  • محل انتشار: چهارمین همایش بین المللی مهندسی ژئوتکنیک و مکانیک خاک ایران
  • کد COI اختصاصی: ICGESM04_259
  • زبان مقاله: انگلیسی
  • تعداد مشاهده: 2147
دانلود فایل این مقاله

نویسندگان

W. G. Brunner

BAUER Maschinen GmbH, Germany

A. Bi

Bauer Technologies Ltd. Taipei, Taiwan

D. Zong

China Water Group, Beijing, China

چکیده

In the South of Sichuan province a 240 MW Yeleh hydroelectric plant was under construction by Sichuan Nanya River Basin Hydraulic Power Development Company Limited, a stateowned enterprise, and China Gezhou Ba Water & Power Group Company Limited. This project sets out to develop the mountain cascade of the Nanya river, a tributary of the Dadu river, provide superior electricity and adjust flood peak & frequency. The specialist contractor Foundation Engineering Company of China Water Resource and Hydropower (FEC) was awarded the contract for foundation treatment at right bank, which included the construction of 75 m deep concrete Cut-Off Wall (COW) inside a 6.0m x 6.5m tunnel. The requirement for 19,317 m3 COW to be constructed in permeable and very dense gravel/cobble formations and a demanding project programme led FEC to adopt Bauer Low Headroom Cutter CBC25/MBC30 in conjunction with Overlap Cutter Joint (OCJ).

کلیدواژه ها

Dam, earth-fill dam, cut-off wall, trench cutter, low headroom cutter

مقالات مرتبط جدید

اطلاعات بیشتر در مورد COI

COI مخفف عبارت CIVILICA Object Identifier به معنی شناسه سیویلیکا برای اسناد است. COI کدی است که مطابق محل انتشار، به مقالات کنفرانسها و ژورنالهای داخل کشور به هنگام نمایه سازی بر روی پایگاه استنادی سیویلیکا اختصاص می یابد.

کد COI به مفهوم کد ملی اسناد نمایه شده در سیویلیکا است و کدی یکتا و ثابت است و به همین دلیل همواره قابلیت استناد و پیگیری دارد.