Flexibility-Based Congestion Management Considering Consumers' Inconvenience Cost of Demand Response Programs

  • سال انتشار: 1403
  • محل انتشار: مجله بهره برداری و اتوماسیون در مهندسی برق، دوره: 12، شماره: 4
  • کد COI اختصاصی: JR_JOAPE-12-4_007
  • زبان مقاله: انگلیسی
  • تعداد مشاهده: 97
دانلود فایل این مقاله

نویسندگان

V. Rahi

Department of Electrical Engineering, Shahid Bahonar University of Kerman, Kerman, Iran

A. Abdollahi

Department of Electrical Engineering, Shahid Bahonar University of Kerman, Kerman, Iran

E. Heydarian-Forushani

Department of Electrical and Computer Engineering, Qom University of Technology, Qom, Iran

M. Rashidinejad

Department of Electrical Engineering, Shahid Bahonar University of Kerman, Kerman, Iran

A. Sheikhi Fini

Power System Planning and Operation Research Department, Niroo Research Institute, Tehran, Iran

چکیده

One of the most important challenges of smart grids is the congestion of transmission lines. A flexible smart grid with demand-side resources can be a suitable solution to manage transmission lines congestion. This paper proposes a multi-objective model with the aim of congestion management through generation rescheduling considering cost and emission purposes in a flexible smart grid. An inconvenience cost for consumers is defined to model the consumers’ unsatisfactory as a consequence of participating in demand response programs (DRPs). Furthermore, a smart grid flexibility index (SGFI) has been presented to show the available flexibility of smart grid as a result of DRPs and gas turbine generators as fast response resources. The DRPs could increase the flexibility of the smart grids due to their impact on flattening the load curve, but this may cause some inconveniences for consumers. On the other hand, participation of consumers in DRPs and the power output gas turbine  are associated with uncertainty. In this paper, the uncertainty of consumer's participation in the DRPs has been modeled by Fuzzy-Markov. The proposed multi-objective particle swarm optimization (MOPSO) has been implemented on the IEEE ۳۰-bus system. The results show that the total operation cost including the generation cost, DRP cost, inconvenience cost of consumers, and pollution is reduced. In fact, the share of generation of expensive generators is reduced.

کلیدواژه ها

Congestion management, Consumer's unsatisfactory, Demand response programs (DRP), Generation rescheduling, Smart grid flexibility index (SGFI)

اطلاعات بیشتر در مورد COI

COI مخفف عبارت CIVILICA Object Identifier به معنی شناسه سیویلیکا برای اسناد است. COI کدی است که مطابق محل انتشار، به مقالات کنفرانسها و ژورنالهای داخل کشور به هنگام نمایه سازی بر روی پایگاه استنادی سیویلیکا اختصاص می یابد.

کد COI به مفهوم کد ملی اسناد نمایه شده در سیویلیکا است و کدی یکتا و ثابت است و به همین دلیل همواره قابلیت استناد و پیگیری دارد.